Project Name:FACOR Project - Sintering & Smelting Plant
Weight:220 tons (2 sets)
Duration:June 2024 - January 2025
Project:Fabrication and supply of preheating kiln and combustion chamber
Location:India
Client:Metso OY
FACOR Sintering & Smelting Plant Project, India
  • Raw materials procured in accordance with Chinese national (GB) standards
  • Welding procedures executed to comply with EN 1090-2 requirements
  • Fabrication of structural steel and plate assemblies with workshop pre-assembly
  • Surface coating and painting treatment
  • Packaging suitable for 40-foot flat rack containers (40FR) and breakbulk shipment
  • Trade terms: EXW (Ex-Works, Yinglong facility)
Fabrication
Fabrication
Pre-Assembly of Preheating Kiln
Pre-Assembly of Preheating Kiln
Pre-Assembly of Combustion Chamber
Pre-Assembly of Combustion Chamber
Stud Welding
Stud Welding
Packaging
Packaging
Packaging for Shipment
Packaging for Shipment